モンテカルロ不確実性解析とベイズ推論による PWR 炉心シミュレーションの改善
Improving PWR core simulations by Monte Carlo uncertainty analysis and Bayesian inference
Improving PWR core simulations by Monte Carlo uncertainty analysis and Bayesian inference
@misc{castro2016improving,
title = {Improving PWR core simulations by Monte Carlo uncertainty analysis and Bayesian inference},
author = {Emilio Castro and Carolina Ahnert and Oliver Buss and Nuria Garcia-Herranz and Axel Hoefer and Dieter Porsch},
year = {2016},
eprint = {1601.08036},
archivePrefix = {arXiv},
primaryClass = {nucl-th},
url = {https://arxiv.org/abs/1601.08036}
}
Castro, E., Ahnert, C., Buss, O., Garcia-Herranz, N., Hoefer, A., & Porsch, D. (2016). Improving PWR core simulations by Monte Carlo uncertainty analysis and Bayesian inference [Preprint]. arXiv. https://doi.org/10.48550/arXiv.1601.08036
CASTRO E, AHNERT C, BUSS O, et al. Improving PWR core simulations by Monte Carlo uncertainty analysis and Bayesian inference[EB/OL]. (2016-01-29)[2026-11-29]. https://arxiv.org/abs/1601.08036.
要旨
PWR 原子力発電所の運転パラメータ予測に、モンテカルロに基づくベイズ推定モデルが適用された。この非摂動枠組みでは、微視的核データの不確実性を記述する高次元共分散情報と、測定された原子炉運転データを組み合わせ、硼濃度低下曲線や燃焼度依存の原子炉出力分布といった積分パラメータの統計的に妥当で根拠のある不確実性評価を提供する。本手法の性能は、盲検テストアプローチで評価され、与えられた原子炉サイクルの測定値を用いて、次期サイクルの予測を改善した。結果、予測品質の向上は顕著である。特に、原子炉サイクル長の計画において極めて重要である硼濃度低下曲線の予測不確実性は、前サイクルの硼濃度測定情報を分析に含めることで、1 桁減る。さらに、非摂動核データ更新の初期結果を提示し、更新されたライブラリを用いて得られる予測は、ベイズ推定を直接積分観測量に適用して得られる予測と整合していることを示した。
A Monte Carlo-based Bayesian inference model is applied to the prediction of reactor operation parameters of a PWR nuclear power plant. In this non-perturbative framework, high-dimensional covariance information describing the uncertainty of microscopic nuclear data is combined with measured reactor operation data in order to provide statistically sound, well founded uncertainty estimates of integral parameters, such as the boron letdown curve and the burnup-dependent reactor power distribution. The performance of this methodology is assessed in a blind test approach, where we use measurements of a given reactor cycle to improve the prediction of the subsequent cycle. As it turns out, the resulting improvement of the prediction quality is impressive. In particular, the prediction uncertainty of the boron letdown curve, which is of utmost importance for the planning of the reactor cycle length, can be reduced by one order of magnitude by including the boron concentration measurement information of the previous cycle in the analysis. Additionally, we present first results of non-perturbative nuclear-data updating and show that predictions obtained with the updated libraries are consistent with those induced by Bayesian inference applied directly to the integral observables.